#NorthInnerCity Traffic & Works Update – March 12th

TEMPORARY ROAD CLOSURES:
Dominick Place, Dublin 1:
• Dominick Place (from Dominick Place to Dominick St Lower) Dublin 1 from Midnight on Tuesday 15th February 2022 to Midnight on Saturday 19th March 2022.
• Closed to facilitate the installation of drainage works and road re-surfacing.
• Pedestrian and local access to be maintained.
Dominick Street Lower, Dublin 1:
• Dominick Street Lower (from Parnell Street to Dorset Street Upper), Dublin 1 from 8am to 8pm, daily between Monday 14th March 2022 and Wednesday 16th March 2022.
• Closed to facilitate water upgrade works.
• South bound traffic via Bolton Street and Kings Inn Street
• North bound traffic via Bolton Street/Dorset Street/ St. Mary’s Place North/ Mountjoy Street/ Blessington Street/ North Fredericks Street/Parnell Square East/Parnell Street
• Pedestrian and local access to be maintained.
St Patrick’s Festival
• St. Patrick’s Day Parade
• Location A:
• Western Way (Dominick St Upr to Mountjoy St) from 19.00hrs on Wednesday 16th March 2022 to 15.00hrs on Thursday 17th March 2022.
• Location B:
• Mountjoy St, Mountjoy St Middle, Palmerstown Place, Wellington St, St Mary’s Place North, Granby Row, Parnell Sq North, Parnell Sq East, Cavendish Row, O’Connell St Upr & Lwr, O’Connell Bridge, Westmoreland St, College Green, Dame St, Lord Edward St, Christchurch Place Nicholas St, Patrick St, New St South, Clanbrassil St Lwr, Kevin St Upr, Kevin St Lwr, Cuffe St and St Stephens Green South from 04.00hrs to 18.00hrs on Thursday 17th March 2022.
• Traffic on Ellis Quay travelling north and east will be diverted via Blackhall Place, Stoneybatter, Manor Street, Prussia Street, North Circular Rd, Portland Row, Seville Place and Guild Street
• Traffic on North Wall Quay travelling south will be diverted via Moss Street, Townsend Street and Lombard St
• Traffic on North Wall Quay travelling west will be diverted via Guild Street, Seville Place, Portland Row, North Circular Rd, Phibsborough Road, Constitution Hill, King Street North and Queen Street.
• Pedestrian access to be maintained.
• St. Patrick’s Festival – St Patrick’s Festival Funfair
• Custom House Quay (Beresford Place to Memorial Road) from 19.00hrs on Wednesday 16th March 2022 to 06.00hrs on Monday 21st March 2022.
• A signed diversion route will be put in place.
• Pedestrian and local access to be maintained.
• St. Patrick’s Festival – St Patrick’s Festival Quarter
• Liffey Street West (Wolfe Tone Quay to Benburb Street) Dublin 7 from 11.00hrs on Wednesday 16th March 2022 to 23.00hrs on Sunday 20th March 2022.
• A signed diversion route will be put in place.
• Pedestrian and local access to be maintained.
• For any further information, please contact Darren Murphy (St Patricks Festival) @ Tel. +353 86 0711207
DISRUPTIONS #NORTHINNERCITY
Dominick Street Lower, Dublin 1:
Works Involved: Installation of drinking water
Date of Works: March 12th – 13th
Contractor: GMC Utilities / Irish water
Dorset Street:
Junction with Eccles Street – Frederick Street
Works Involved: Sewer relining
Date of Works: March 14th – 20th, 7pm – 5am.
Contractor: GMC Utilities / Irish water
Dublin Port Tunnel:
Entire length
Works Involved: Full closure.
Date of Works: March 15th – 16th, 10pm – 5am.
Guild Street:
Sheriff Street – Mayor Street
Works Involved: Sewer cleaning
Date of Works: March 14th – 16th, 7pm – 5am.
Contractor: Irish Water / GMC Utilities
Harold Road
Works Involved: Build 8 Tree Pits on road verge, removal of 8 car parking space.
Date of Works: March 12th – 18th.
Contractor: MCD Landscapes Ltd.
North Circular Road
Outside 273 – opposite junction with Rathdown Road and Nos. 231, 258, 446, 561
Works Involved: Footpath Reinstatement
Date of Works: March 12th.
Contractor: Irish Water / GMC Utilities
North Wall Quay
Junction of North Wall Avenue
Works Involved: Pressure management
Date of Works: March 12th – 13th.
Contractor: GMC Utilities Group
Ormond Quay Lower
No. 4/ 4A
Works Involved: Lay Domestic Gas Service
Date of Works: March 13th
Contractor: Gas Networks Ireland / GMC Utilities.
Ostman Place
Works Involved: Build 8 Tree Pits on road verge, removal of 8 car parking space.
Date of Works: March 12th – 18th.
Contractor: MCD Landscapes Ltd.
Poplar Row
At No. 3
Works Involved: Reinstating Works
Date of Works: March 12th – 13th.
Contractor: ESB / Richard Nolan Civil Engineering.
Queen Street
Bargaintown
Works Involved: Lay Commercial Gas Service
Date of Works: March 13th.
Contractor: Gas Networks Ireland / GMC Utilities