TEMPORARY ROAD CLOSURES:
Dominick Place, Dublin 1:
– Dominick Place (from Dominick Place to Dominick St Lower) Dublin 1 from 00.00hrs on Tuesday 15thFebruary 2022 to 24.00hrs on Saturday 19th March 2022.
– Closed to facilitate the installation of drainage works and road re-surfacing.
– Pedestrian and local access to be maintained.
DISRUPTIONS #NORTHINNERCITY
Beresford Place:
From under railway bridge to Gardiner Street Lower junction.
Works Involved: Removal of Cobble from Central median between the road and the Luas line.
Date of Works: 26th – 27th February.
Contractor: MCD Landscapes Ltd.
Charlemont Parade / Ulster Terrace:
Various locations.
Works Involved: sawcut & excavate with mini digger the footpath & reinstate with concrete.
Date of Works: 26th February – 2nd March
Contractor: DCC Road Maintenance/ RNCE
Clonliffe Road:
Junction of Drumcondra Road.
Works Involved: Pressure Management
Date of Works: 26th – 27th February.
Contractor: GMC Utilities Group / Irish Water.
Clonmore Road:
Various locations.
Works Involved: sawcut & excavate with mini digger the footpath & reinstate with concrete.
Date of Works: 26th February – 2nd March.
Contractor: DCC Road Maintenance/ RNCE.
Clonmore Terrace:
Various locations.
Works Involved: sawcut & excavate with mini digger the footpath & reinstate with concrete.
Date of Works: 26th February – 2nd March.
Contractor: DCC Road Maintenance/ RNCE.
Dorset Street Upper:
From Eccles Street – Frederick Street
Works Involved: Sewer relining.
Date of Works: 28th February – 6th March, 7.00pm – 5.00am.
Contractor: Irish Water / GMC Utilities.
Dublin Port Tunnel:
Entire length
Works Involved: South Bore closure only
Date of Works: February 28th – March 2nd, 10pm – 5am.
Dublin Port Tunnel:
Entire length
Works Involved: Full closure
Date of Works: Wed 2nd – Fri 4th March, 10pm – 5am.
Guild Street:
To junction with Sheriff Street.
Works Involved: Telecoms Works
Date of Works: Tuesday 1st March, 7.30pm – 11pm.
Contractor: TSS /Freeflow Traffic Management.
Guild Street:
Between North Wall Quay – Sheriff Street.
Works Involved: Sewer cleaning
Date of Works: 2nd – 3rd March, 7.00pm – 5.00am.
Contractor: Irish Water / GMC Utilities.
Harold Road:
Works Involved: Build 8 Tree Pits on road verge.
Date of Works: 28th February – 4th March.
Contractor: MCD Landscapes Ltd.
North King Street:
Outside 48-59 North King Street.
Works Involved: Water mains repair.
Date of Works: 28th February, 7pm to 11pm.
Contractor: GMC Utilities.
Little Green Street:
At 1A
Works Involved: Reinstating Works.
Date of Works: 26th February.
Contractor: ESB/ Richard Nolan Civil Engineering.
North Circular Road:
Outside 1, 90, 231, 258, 273, 284, 296 & junction of Aughrim Street.
Works Involved: Footpath reinstatement
Date of Works: 26th February.
Contractor: Irish Water / GMC Utilities.
North Strand Road /Charleville Mall at the Royal Canal:
Works Involved: Placement of mobile crane to facilitate removal & replacement of gates.
Date of Works: On-going until February 28th.
Contractor: Waterways Ireland.
Ostman Place:
Works Involved: Build 8 Tree Pits on road verge, removal of 8 car spaces.
Date of Works: 28th February – 4th March.
Contractor: MCD Landscapes Ltd.
Prussia Street:
No. 79-84
Works Involved: Trenching and Ducting.
Date of Works: 26th February – 1st March.
Contractor: ESB/ Richard Nolan Civil Engineering.
Sheriff Street Upper:
Coopers Cross
Works Involved: Road Resurfacing
Date of Works: 26th February.
Contractor: Gas Networks Ireland / GMC Utilities.
Categories
Arbour Hill, Ballybough, Broadstone, Church Street, City Centre, Clonliffe Road, Constitution Hill, Dublin City Council, East Wall, Grangegorman, Infirmary Road, Markets, Montpelier, North Circular Road, North Strand, North Wall, Planning, Quays, Rathdown Road, Sean McDermott Street, Smithfield, Stoneybatter, Summerhill, Transportation
raymcadam View All
Fine Gael Councillor - North Inner City
Chair, Urban Form & Planning Strategic Policy Committee