#NorthInnerCity Greening Strategy – 2021 Progress Report

Gloucester Place Road Re-alignment and SUDS Pilot Project.
Design Complete and Construction Tender pack has been issued to the Landscape/Minor Civils Framework and was received back on the 6th of August. Tender assessment is now complete and contractors appointed and awaiting construction program and traffic management plans. Work to be completed during quarter 4 2021.
Oriel Street Plaza/Pocket Park
Design Complete and Construction Tender pack has been issued to the Landscape/Minor Civils Framework and was received back on the 13th of August. Tender assessment is now complete and contractors appointed and awaiting construction program and traffic management plans. Work to be completed during quarter 4 2021.
Beresford Central Median
Design Complete and Construction Tender pack has been issued to the Landscape/Minor Civils Framework. Tender assessment is now complete and contractors appointed and awaiting construction program and traffic management plans. Work to be completed during quarter 4 2021.
Memorial Road/Amiens Street Traffic Island (Bus Aras)
Design Complete and Construction Tender pack has been issued to the
Eastwall Recreational Centre/Park
We already have concepts for this project based on layouts prepared within the NEIC Greening Strategy document. The next stage is to initiate public consultations and workshops to get residents and local feedback. It is anticipated that the consultation phase will commence before year end (dependant on Covid regulations).
Annesley Avenue
Tenders returned and contract awarded. Due on site in October. Awaiting construction program and traffic management plans.
Fourth Road
Tenders returned and contract awarded. Due on site in October. Awaiting construction program and traffic management plans.
Landscape/Minor
Civils Framework and was received back on the 13th of August. Tender assessment is now complete and contractors appointed and awaiting construction program and traffic management plans. Work to be completed during quarter 4 2021.
Dorset Street Central Median – Phase two
Tenders returned and contract awarded. Due on site in October. Awaiting construction program and traffic management plans.
Suicide Plot – Biodiversity Garden
Complete and under current maintenance of contractor
Sackville Place Biodiversity Garden
Contractor appointed and works are on going.
O’Connell’s Secondary School Greening Grant (Outdoor classroom)
Contractor appointed and Polytunnel installed. Raised beds and benches installed.
Clonmore Road Residential Street Greening
All site investigations complete. Concepts drawings currently being prepared and consultation will commence with residents as soon as possible and dependant on Council and government Covid regulations.
Buckingham Street
Áit Landscape Architects currently carrying out a feasibility study and concepts for a proposed new street design and linear park for Buckingham Street. It is anticipated that this project will be ready for presentations in Quarter 4.
Poplar Row (Minor Central Median)
Concepts prepared and quotes received. Works will commence shortly.
Covid 19 public health restrictions have had an impact on the timeframe of some of the above projects, however, focus is now on keeping pace to work towards delivery or substantial completion of all 2021 funded projects before year end.
No formal discussions have yet commenced on potential 2022 projects to be presented to the NEIC Board for approval in due course. Many factors will be taken into account in the selection of projects but the intention is to keep in line generally with the NEIC Greening Strategy 2018-2026.
The projects will include some residential greening initiatives and public representations in this regarding will be taken into account.
Categories
Ballybough, City Centre, Clonliffe Road, Dublin City Council, East Wall, Fine Gael, North Circular Road, North Strand, North Wall, Planning, Sean McDermott Street, Urban Form
raymcadam View All
Fine Gael Councillor - North Inner City
Chair, Urban Form & Planning Strategic Policy Committee